Project Update – Bennington High School Addition

Although progress may feel slow at times, we’re still making strides at Bennington High School.  As of last week, the double wall spiral had been installed in the spacious new auxiliary gym.  The Alliance Air rooftop units have been set and are actively being tied in.  Currently underway:  Hot and chilled water piping; Trane building automation system.

Take a peek at the snapshot below showing the progress to date!  We’re still aiming for a completion date sometime in March.  Roll on, team!

Bennington High School double wall spiral installed in gym

Double wall spiral installed in the gym.